How Was the Muskegon Lake Brownfield Remediation Fixed?

Muskegon Lake, a 4,149-acre drowned river mouth lake flowing into Lake Michigan, faced profound environmental damage from over a century of industrial activity. This degradation severely impaired the health of the waterbody and its ecosystem, necessitating a massive environmental cleanup effort. The comprehensive restoration of this Great Lakes tributary became a model for how federal, state, and local partnerships can reverse severe environmental decline.

The History of Industrial Contamination

The environmental decline of Muskegon Lake began in the mid-1800s during the lumber era. Nearly 50 sawmills operated along the shoreline, dumping massive amounts of sawdust, slab wood, and other logging debris directly into the water. This waste began filling in shallow areas and wetlands.

Following the lumber boom, the area transitioned into a center for heavy industry, including foundries and chemical processing plants. These factories continued using the lake as a waste repository, introducing new, more toxic pollutants. Waste included foundry slag, industrial wastewater, and various chemical byproducts.

Decades of unregulated disposal resulted in contaminated sediment and plummeting water quality. The continuous dumping and infilling ultimately reduced the lake’s surface area by an estimated 16%, replacing natural shoreline and wetlands with artificial, contaminated fill. This historical contamination required large-scale federal intervention.

Defining the Area of Concern and Remedial Goals

The extent of the contamination led to the formal designation of Muskegon Lake as a Great Lakes Area of Concern (AOC) in 1987 under the Great Lakes Water Quality Agreement. This designation identified the lake as one of the most environmentally degraded sites in the Great Lakes basin. Contaminants included heavy metals (mercury and lead), petroleum hydrocarbons, and toxic organic compounds such as Polychlorinated Biphenyls (PCBs) and Polycyclic Aromatic Hydrocarbons (PAHs).

The Remedial Action Plan (RAP) established nine specific Beneficial Use Impairments (BUIs) that had to be addressed to restore the lake’s health. Initial impairments included restrictions on dredging activities, degradation of the bottom-dwelling organism community, and restrictions on the consumption of fish and wildlife.

The goal was to systematically remove these nine impairments by cleaning the environment to meet specific targets. This required a multi-phase approach involving the Michigan Department of Environment, Great Lakes, and Energy (EGLE) and the U.S. Environmental Protection Agency (EPA). The plan focused on removing pollution sources and restoring damaged aquatic habitats to their natural function.

Implementation of Remediation Technologies

The cleanup involved a combination of methods focused on contaminated sediments and upland source control. The Great Lakes Legacy Act (GLLA) provided federal funding for these complex operations. Over the course of the project, partners remediated approximately 190,000 to 200,000 cubic yards of contaminated sediment from the lake bottom.

The most polluted areas, often called “hot spots,” were addressed through mechanical dredging. This involved excavating sediment, such as the 10,600 cubic yards removed from the Ryerson Creek Outfall. The dredged material was transported to specialized confined disposal facilities (CDFs) to ensure permanent isolation from the environment.

Capping was employed as a secondary remediation method for areas with lower contaminant concentrations. This technique involved placing a layer of clean material, such as sand or clay, over the contaminated sediment. The cap physically isolates the pollutants, preventing them from mixing with the water column or being consumed by aquatic life.

Source control measures were also implemented to prevent future re-contamination. This included cleaning up adjacent brownfield sites, like the Zephyr Refinery property, which contributed petroleum and metal-impacted sediments. Additionally, a massive effort removed over 110,000 tons of historical logging debris and unnatural fill that had degraded the lake bottom.

Measuring Success and Delisting Progress

Success was measured through a monitoring process that tracked environmental health indicators against the established BUI removal criteria. Scientists conducted extensive sediment sampling and water quality testing to confirm contaminant levels were reduced to safe thresholds. Biological indicators, such as the health and diversity of the benthic macroinvertebrate community, were also monitored to demonstrate ecological recovery.

The removal of the Beneficial Use Impairments was a phased process. The first BUI, Restrictions on Dredging Activities, was removed in 2011 after contaminated sediment was addressed in the navigational channel. Later successes included the removal of the Restrictions on Fish and Wildlife Consumption BUI and the Beach Closings BUI as water quality improved.

The final BUI, Degradation of Benthos, was removed in October 2024, signifying a healthy recovery of the lake’s bottom-dwelling organisms. With all nine impairments addressed, the Muskegon Lake AOC became eligible for delisting. The AOC was formally delisted in September 2025, marking the completion of the decades-long restoration effort.

The environmental recovery is yielding significant community benefits, including the restoration of 134 acres of fish and wildlife habitat. Improved environmental health and public access are projected to increase local property values by nearly $8 million. The restoration is also estimated to boost the local recreation and tourism economy by $28 million annually.